Construction quantities, read straight out of CAD drawings.

A bill of quantities takes an engineer weeks by hand. This reads the drawing file and computes the same numbers, then scores itself against the one a real firm produced. 7 of 8 line items land within ±10%.

pick a material, then compute
Pipeline
0
Engineer’s BOQ
0
ground truth
Error
0%

Every line, scored

ItemSheetPipelineBOQError
Precast pilesS2.0166660.0%
Structural concrete — foundationS2.0153.153.00.2%
Formwork — foundationS2.01249.7296.015.6%
Sand blindingS2.0114.014.00.1%
Lean concreteS2.017.07.00.1%
Structural concrete — level 1S2.02143.8153.06.0%
Structural concrete — level 2S2.03144.5143.01.1%
Structural concrete — level 3S2.0468.068.00.0%
Formwork — level 2S2.031327.21356.02.1%